Greenhams Tongala

ClientCAF Build

DurationApril 2023 to November 2023

Project Value: $1.3 million

Steel Tonnage: 39t

Project Scope: 

CG&C Group businesses Connex, CPE Construction and CGC Site Services were engaged to complete upgrade works to the Greenham Tongala Facility,

One part of the scope involved the installation of a new cow race and CG&C Group was given the target of completing shop drawings, procurement, fabrication, galvanizing, and installation within 1 month to meet the facility opening date,

CG&C Group used its accelerated design process to commence procurement whilst shop drawings were still being completed,

Both Connex and CPE Construction worked overtime during weekends to ensure that the program stayed on track,

CG&C Group worked closely with long standing suppliers Infrabuild and Furphy Galvanizing to ensure a quick lead times on steel processing and galvanizing,

Finally, CGC Site Services received weekend delivery of the steelwork and completed installation in time for the opening,

This project proved to be a robust test of the group’s processes and ability to adapt to a fast-paced delivery,