Client: Vic Connect
Duration: April 2022 – May 2023
Project Value: $2.19m
Steel Tonnage: 56t
Project Scope:
The project included the structural steel and cladding of the platform canopies and stairs at Bunyip, Longwarry and Morwell stations.
With the project based in Gippsland, it proved a logistical challenge to complete this job, especially due to the frequency of wet weather days throughout the installation works.
Another major obstacle on this project was the frequency of trains during the installation, this meant only small windows of time were allowed to install the platform canopies.
Despite all of the challenges on this project, CPE Construction was able to deliver a quality product.