Client: Coleman Rail
Duration: September 2021 – November 2023
Project Value: $4.8 million
Steel Tonnage: 90t
Project Scope:
CG&C Group businesses Connex, CPE Construction, and CGC Site Services were engaged to complete the structural steel and building packages at the Shepparton Stabling as well as some other minor packages across the project.
The Shepparton Stabling Yard works were part of the critical path for the entire project and as such, achieving handover dates was essential,
Using the integration within the businesses, CG&C Group were able to reduce delivery timeframes for key steel elements that help reduce the overall program.
CPE Construction also managed key subcontractors across various trades (Electrical, Plumbing, Carpentry, Glazing, Flooring, Tiling, Roofing/Cladding) to ensure continuity of progress and any interface risks,
During the project there were numerous design and architectural issues that CG&C Group assisted the client by finding cost effective and timely solutions, this was a key factor in delivering a successful outcome for the client.