Client: JC Butko
Duration: February 2015 – May 2016 & April 2017 – July 2018
Project Value: $4.8 Million
Project Scope:
Supply and installation of structural steel, roof/wall cladding and louvres for 2x towers 1 @ 36m high, 1 @ 32m high. Due to height of towers this necessitated the development of lifting technique for wall sheets to ensure that sheets could not be dropped during the installation process whilst still ensuring they could be installed efficiently.
Due to the size of processing equipment within the structures CPE need to work closely with the other trades onsite to ensure that no element was going to be built out prior to commencing the floor above.