November 2024

Northwood Stable

Client: Seymour Equine Services Duration: July 2024 – August 2024 Project Value: $145k Steel Tonnage: 1.7t Project Scope:  The project involved all of the companies within the CG&C Group. GMCE completed the engineering and design with Connex completing the shop drawings. Due to the extremely tight timeframes on the project, the group’s accelerated design process was used (completing […]

Northwood Stable Read More »

Webb Street Level Crossing Removal Project (Narre Warren Station)

Client: Built Environs Duration: April 2023 – June 2024 Project Value: $10.8m Steel Tonnage: 575t Project Scope:  CG&C Group businesses GMCE, Connex, CPE Construction, and Concept Rigging were engaged to complete the structural steel and platform cladding packages, The total value of work completed was $10.8m and included 575t of steel, Connex completed the shop drawings, whilst

Webb Street Level Crossing Removal Project (Narre Warren Station) Read More »

Mount Derrimut Road Level Crossing Removal Project (Deer Park Station)

Client: Built Environs Duration: October 2022  to October 2023 Project Value: $5.2 million Steel Tonnage: 215t Project Scope:  CG&C Group businesses CPE Construction and Concept Rigging were engaged to complete the buildings steel, stairs and ramps steel, and stair cladding works. Of significance in this package was the fabrication and installation of the Bunjil Canopy, The architectural complexity involved

Mount Derrimut Road Level Crossing Removal Project (Deer Park Station) Read More »